| The Historic Atlantic
City Convention Hall, now commonly
referred to as the Atlantic City Boardwalk
Hall, was listed on the United State
Register of Historic Places as a National
Historic Landmark on February 27,
1987. As a result, all work performed
in the building must be executed in
compliance with the Secretary of the
Interior's Standards for the Treatment
of Historic Properties.
 |
| (above):
Interior view of Atlantic
City's Boardwalk Hall |
|
The design of the restoration and
rehabilitation process identified
many challenges that needed to be
addressed in order to transform the
building into a modern day special
events center. Some of the major challenges
included the abatement of asbestos
fire-proofed space behind ceiling
tiles, and a complete replacement
of the barrel vaulted ceiling in an
historically accurate fashion.
As originally created, the building
was not designed to accommodate present-day
production standards and efficient
use of space. The structural improvements
addressed accessibility for rigging,
lights and sound equipment; newer,
wider and more comfortable seating
with acceptable sight lines between
the lower edge of the balcony and
the floor level; and improved use
of corridor space, modern back-of-house
facilities and guest accommodations.
Work on the
building commenced in November, 1998,
and has been completed in five phases:
Phase 1 -
Construction of scaffolding for
ceiling reconstruction
Phase 2 - Removal of ceiling and
asbestos abatement
Phase 3 - Reconstruction of ceiling
Phase 4 - Construction of arena
bowl and restoration of historic
features
Phase 5 - Special Event Center Fit
Out and Finishes
The $90 million renovation to transform
historic Boardwalk Hall into a state-of-the-art
special events arena was completed
under the auspices of the New Jersey
Sports and Exposition Authority, the
building's owner. The facility is
operated by the Atlantic City Convention
and Visitors Authority and managed
by SMG.
Scaffolding and reconstruction
of the ceiling and lighting system
Due to the unique nature of the arched
137- foot clear span barrel ceiling,
the project's architectural firm Ewing
Cole worked with Tishman Construction
to devise an innovative hung. scaffolding
system that was suspended from the
existing roof trusses. Approximately
36,000 square feet of custom-designed
moveable scaffolding was suspended
from the underside of the roof structure
and moved from each of the ten 50-foot
bays along the length of the building.
Support beams were added at strategic
locations within the box trusses,
and trolley beams. were suspended
to carry the traveling scaffolding
platforms. The system provided workers
safe access for the ceiling restoration,
and allowed for the removal and replacement
of the existing ceiling without inhibiting
other construction below or hindering
the Miss America Pageant. Work on
the ceiling was completed on September
14, 2000.
The original acoustical ceiling tiles,
constructed of sugar cane, were spray
painted after installation with aluminum
paint, allowing the ceiling to act
as a giant lighting reflector. Over
time, the tiles sustained damage from
water and rigging. Because of asbestos
contamination, flammability of the
sugar cane fiber and the tile's deterioration,
new tiles replicating the original
look but constructed of substitute
materials have been installed. Metal
pan ceiling tiles were selected for
the bays and underside of the trusses;
the tiles on the sides of the trusses
are constructed of glass-fiber reinforced
gypsum (GRG). Nearly 23,000 metal
pan tiles and 3,600 GRG panels were
installed. The size, color, surface
texture and reflectant have replicated
the original effects. The wood ceiling
moldings were removed, then replicated
and reinstalled in metal on the tiles.
The frames of the 540 lighting windows
in the sides of the trusses were removed
and replicated in GRG. The glass panes
of the lighting windows were disassembled,
restored and reinstalled. Some of
the original glass assemblies remain
intact and have been installed on
the south side of the trusses more
visible to the audience. Ventilation
louvers that surround each of the
540 window sashes have been redesigned
as part of the new HVAC system and
replicated to the original louvers.
Behind the original truss lighting
windows were 1,500 watt incandescent
projector lamps that shone through
colored gel filters. A panel in the
stage house controlled the lighting
and gel filters, but this system was
abandoned three years after installation
due to maintenance expenses. Pendant
lights were later installed along
the sides of the trusses, but blocked
a view of the ceiling for the audience.
The restoration has recreated the
original effect with modern technology.
All lighting is now computer controlled.
The ceiling bays are lit indirectly
by space cannons at the top of the
loggia and the truss lighting windows
are backlit.
To allow more than 130,000 pounds
of special theatrical equipment, production
lighting and sound equipment to be
hung, the existing 335-foot span trusses
were strategically reinforced, with
additional load capacity for other
specialty rigging. A complex system
of hoist motors and pulleys were coordinated
and supported within the ceiling cavity
to provide an operable and flexible
system for the center hung scoreboard,
speakers and rigging grids.
Upper Balcony Concourse
At the base of the ceiling along the
east and west concourses is the balcony
upper concourse. It is enclosed by
a loggia defined by sets of tripartite
arches supported by four columns and
set between the arched trusses. The
tripartite arches have plaster column
capitals that depict land and sea
creatures. On the south end, twelve
loggia columns and capitals were removed
when the mechanical rooms were constructed
in 1960. Set into the loggias of the
fourth bay and into the ceiling above,
are ornate composite material grilles
which are part of the Midmer-Losh
organ chambers. The concourse, exterior
surface of the grilles, extant arches,
columns and capitals have been restored
and repainted in historically correct
colors.
State Seals
The seals of 48 states and territories,
and the Great Seal of the United States,
are located in the spandrels of the
loggia. The seals were painted on
canvas then applied to the walls.
The state seals have been restored
and repainted. During the restorative
process, artists repaired any tears
or damage to the seals, then cleaned
the seals by removing the top layer
of varnish and used exposure windows.
to examine the seals for original
colors under the paint and varnish.
Balconies
The original shallow and steep balcony
cantilevered out from the sidewalls
below the loggia and balcony upper
concourse. The balconies below the
loggia did not follow the rhythm of
the ceiling trusses in the arrangement
of seats, aisles, vomitoria and fascia
design. In order to construct a contemporary
arena bowl large enough to hold the
required number of seats, arranged
in a layout that accommodates present
day expectations for sight lines,
it was necessary to remove the balconies.
As originally constructed, the leather
and walnut fixed seats in the balconies
bore the Atlantic City Convention
Center seal and date of construction.
Because these seats were smaller than
current standards and in questionable
condition, they are not being reused
for public seating in the hall. Identical
seating, restored in the 1980's, remains
in place in the Adrian Phillips Ballroom
balcony.
The musician.s balcony was originally
set into the seating balconies at
the south end, opposite the stage.
This space was removed along with
the rest of the balconies, and a new
balcony, closer to the arena floor,
was constructed, making visual reference
to the original.
Proscenium Pylons, Arch, Leaded
Glass Globe and Insert, Curtains and
Valance
The proscenium opening is framed on
each side by Neo-Assyrian-style pylons
rising 88 feet above the Auditorium
floor, and cleaved at the top with
opposite facing eagles. Above the
pylon cornice is a 16-foot high capital
with cornice and stepped roof. The
capitals feature leaded glass inserts,
one depicting the shield of the seal
of New Jersey, the other depicting
the shield seal of Atlantic City.
The proscenium arch spans the 104-foot
stage opening at a radius of 137 feet
and 18 feet high. The elaborate façade
features panels bearing basket weave
patterns and graceful moldings. Centered
on the top of the arch is a leaded
glass globe with the letters WPG.
(World's Play Ground) buttressed
with stylized eagles and cornucopias.
A double band of rays rings the upper
hemisphere of the globe.
The proscenium pylons and the cornice
of the proscenium arch are set out
from the end wall by recessed lighting
troughs along the outer jamb and along
the top and sides of the pylon capitals.
The troughs were finished with reflective
aluminum paint and fitted with lampholders
and floodlights. As part of the renovation,
the troughs were restored and rebuilt
and relit with cold cathode lighting.
On the plaster valance of the proscenium
arch is a beautifully designed mythological
mural featuring Neptune and mermaids
in shades of blue, green, and gold,
with rose accents. A portion of the
sky with billowing clouds is rendered
in gold leaf. On the horizon of the
scene, the 1929 skyline of Atlantic
City is depicted
The proscenium has been restored and
repainted in historically correct
colors, and the leaded glass cleaned
and restored.
As work progressed during the restorative
phase, artists confirmed a color study
previously conducted by Watson & Henry
Associates, who studied all the original
colors of the historic aspects of
the building through the use of a
microscope and other lab equipment.
The artists had to match the paint
colors to a chart by creating mock-ups.
The contractor's conservator and the
New Jersey State historic preservation
office then approved the mock-ups.
The stage opening is protected by
a fire curtain. This curtain is painted
in shades of blue, green and gold,
with a scene depicting a medieval
ship at sea, possible one of Columbus.s
ships. Vertical decorative borders
on either side of the ship scene feature
the City of Atlantic City seal. The
safety curtain has been cleaned, repaired
and restored. The valance framed the
proscenium mural.
North End Walls, Grilles and Bracketed
Balconies
Flanking the proscenium are two quadripartite,
round arch openings set above shallow
bracketed balconies and fitted with
elaborate tracery grille, behind which
can be found the pipe organ chambers.
These features have been restored
to their original historically accurate
colors.
Main Floor, Concourse and Seating
Bowl
To allow the new multipurpose event
center to serve a range of events,
the designers created a multi-level
radial - U. shaped seating bowl that
can extend toward the center of the
hall to improve sightlines to the
stage and ice sheet. The new seating
bowl framing is integrated with the
original pile foundations that support
the building structure while the original
architecture of the perimeter arcade
from which the vaulted roof springs
has been preserved.
The bowl is of structural steel framing
- the lightest framing system possible
- supporting precast concrete seating.
The new framing is designed to support
three levels: the balcony, concourse,
and event level. 1100 tons of steel,
2500 cubic yards of poured concrete,
and 650 pieces of pre-cast went into
the construction of the concourse
and seating bowl.
The concourse level framing combines
new and existing steel framing modified
to connect to the lower elevation
of the new steel framing. Several
of the existing concourse level girders
were left in place because they supported
the balcony level framing above; these
were reinforced by field-bolting new
steel angles to the webs of the existing
girders at the lower steel elevation
and by steel WT sections welded to
the bottom of the existing girders.
New connection angles were then field-welded
to the existing framing. Because some
connection angles were oversized with
holes located to clear the existing
connection rivets, connections had
to be field-modified to accommodate
existing rivets and other connection
plates and built-up angles.
The structural design was performed
using the computer software STADD
and RAM.
Removing the Ice Sheet and Support
of the Event Level
The new ice sheet has been centered
in the new bowl layout and on the
existing structural arches. To allow
for better viewing of special events
and to create symmetry of the bowl
as it sits in the space, the existing
rink has been relocated 20 feet closer
to the stage end. The floor framing
and the depressed rink slab areas
in the event floor have been carefully
coordinated with the existing roof
truss ties running continuously through
the width of the floor for 335 feet.
During the course of identifying possible
remedies for the deteriorated underlying
structural slab (probably caused by
brine from the original ice-making
system), the engineering team considered
improving the load-carrying capacity
of the slab as an ancillary benefit.
The new NHL regulation-sized ice rink,
which consists of 400 cubic yards
of concrete, measures 200 feet by
85 feet. Glycol, a refrigerant used
for cooling the floor, runs through
51,200 feet of piping within the arena
floor. The addition of a new refrigeration
plant allows the entire ice surface
for hockey, including the painting
of lines and logos, to be completed
in 24 hours. A rapid de-bonding system
has been installed to facilitate quick
ice removal within eight hours, enabling
a faster conversion from event to
event.
Modern Amenities and Additional
Building Enhancement
Two passenger elevators have been
installed to move patrons from the
basement parking area up to the new
concourse and club areas.
The new concourse curves around the
east, south and west sides of the
Hall, and contains eight permanent
concession stands, twelve public restrooms
and two merchandise areas. The new
flooring is comprised of imported
Tajima tile.
The new seating bowl has been installed
with 10,500 seats; 7,676 permanent
seats, 432 Club Seats; 3,500 telescopic
seats, and approximately 2,200 floor
seats that can be arranged for specific
seating configurations. The Club Seating
area features carpeting, upgraded
seating, a lounge area, and private
food and beverage service. A total
of 13,800 seats has been installed
and can be easily configured to accommodate
a variety of events.
A new video scoreboard and grid have
been designed and added to the arena.
The center-hung scoreboard system
has four full-color, 16mm LED video
screens. The control room is conveniently
located on the arena floor level near
the television support room and TV
truck parking. The house equipment
includes four cameras (two with studio
set ups, one hand held and one wireless
hand held). All have communications
back to the control room. The arched
grid, approximately 104 feet by 87
feet and suspended from the ceiling,
can be lowered to the floor to allow
easy attachment of sound and lighting
equipment. It is capable of hanging
80,000 lbs. of equipment.
Lobby, Box Office and Event Level
Boardwalk Hall's new box office was
created from the former Delegate Lounge.
It is located in the front of the
building and fully accessible from
the Boardwalk. The box office is open
Monday through Saturday from 11 a.m.
to 5 p.m. Other operating hours are
contingent upon scheduled events and
ticket sales. Tickets to all events
at Boardwalk Hall will also be available
by calling TicketMaster for charge-by-phone
service or by logging onto
www.ticketmaster.com
Just off the arena floor are eight
team-size dressing rooms, a Green
Room, two star dressing rooms, an
interview or press room, medical treatment
areas, whirlpool rooms, a new 7,000
square foot kitchen, and 15 new event-level
rest rooms. Also located on the event
level behind the lobby are four meeting
rooms; two each offers 480 square
feet of space and 660 square feet
of space, respectively. New administrative
office suites for the Atlantic City
Boardwalk Bullies hockey team and
Boardwalk Hall operations staff have
also been added.
The offices located on the Mississippi
Avenue side, just off the Boardwalk,
will be made available for future
development of retail space.
Project Team
Architects/Engineers:
Ewing Cole Cherry Brott
Philadelphia, PA
Donald H. Dissinger, AIA, Project
Principal
John H. Sassmann, AIA, Project Manager
William B. McCullough, AIA, Project
Architect
Richard A. Esslinger, PE, Senior Structural
Jared J. Loos, PE, Structural Engineer
Sports Design
Consultant: Rosser International
Atlanta, Georgia
George D. Bushey, AIA, Design Architect
Paul R. Kinzie, AIA, Project Architect
W. Robert P. Ames, AIA, Project Manager
Preservation
Architects/Engineers: Watson
& Henry
Bridgeton, NJ
Penelope S. Watson, AIA, Principal
Architect
Michael C. Henry, PE, AIA, Principal
Engineer/Architect
Leila Y. Hamroun, Project Manager
- Interior Restoration
Geotechnical Engineering Geotech,
Inc
Consultant:
Maple Shade, NJ
Cetin A. Okcuoglu, PE, Chief Principal
Engineer
Signage/Interior Graphic Design: Cloud Gehshan Associates
Philadelphia, PA
Jerome Cloud, Principal
Virginia Gehshan, Principal
Andrew Parsons, Project Designer
Ken Olchewski, Project Design
Clients:
New Jersey Sports & Exposition Authority
East Rutherford, NJ
Casino Reinvestment Development Authority
Atlantic City, NJ
Construction
Manager: Tishman Construction
New York, NY
Ewing Cole Cherry Brott is
an architecture and engineering firm
with offices located in Philadelphia
and Washington, DC. It is nationally
and internationally recognized for
its award winning designs in sports,
recreational, and entertainment facilities.
The firm's sports and entertainment
portfolio includes signature projects
such as the Meadowlands Sports Complex,
Boardwalk Hall, Emerald Downs, and
Singapore Turf Club. |